Stormwater Management

INEAS SD-100:26, clause 7. Preliminary draft.

7 Stormwater management

7.1 General

7.1.1 The SWM design shall address, as the approval authority and site require: quantity control, quality control, erosion control, water balance, conveyance (minor and major systems), and failure and overflow conditions.

7.1.2 Each criterion used shall be stated with its source and edition, and the design shall show the required and provided value for each.

7.1.3 The design shall cover the current development phase. Future phases shall be assessed as a separate scenario.

7.1.4 Where a development changes runoff only slightly, the design shall still quantify pre- and post-development peak flows for each outlet. A finding that the change is negligible shall state the change in flow as a percentage and the measure that offsets it, and shall be accepted by the authority in writing before quantity control is omitted.

7.2 Hydrology

7.2.1 The approval authority's IDF curves and design storms shall be used, with the source cited. Where the site drains to a provincial highway, the MTO IDF Curve Lookup shall be used for that outlet. Where no authority curve exists, the MTO IDF Curve Lookup or the nearest Environment and Climate Change Canada station shall be used, with the choice justified (see CSA PLUS 4013).

7.2.2 Peak flows for sites up to the authority's limit (commonly 5 ha) may be computed by the Rational Method. Larger sites, ponds and multi-outlet systems shall use a hydrograph model (for example, SWMM-based or Visual OTTHYMO).

7.2.3 Storage shall be sized by the Modified Rational Method at the critical storm duration, or by hydrograph routing. The storage method and its assumptions shall be stated. Storage shall not be sized with a storm duration equal to Tc; see 7.2.9.

7.2.4 Runoff coefficients shall be taken from the authority's table where published; otherwise from a cited source (for example, MTO Drainage Management Manual Design Chart 1.07), selected by surface, slope and soil. Weighted coefficients shall be computed by spreadsheet from CAD-measured areas and checked against percent impervious. Where the authority requires it, coefficients shall be increased by 25% for the 100-year storm, to a maximum of 1.0.

Table 7.1 — Runoff coefficients (informative)

Surface

C (2- to 10-year)

Source

Grass / landscaped

0.25

MTO Design Chart 1.07; City of Kingston uses 0.25 for lawns

Pasture, flat (0–5%), loam or silty loam

0.20 (0.22 at 25-year, 0.24 at 50-year, 0.25 at 100-year)

MTO Design Chart 1.07

Gravel

0.40

MTO Design Chart 1.07

Roof

0.90

MTO Design Chart 1.07

Concrete / asphalt

0.90

MTO Design Chart 1.07

Note: Rideau Lakes required C = 0.70 for compacted gravel driving and parking surfaces. Gravel shall be assigned by its condition: 0.40 for loose or landscaped gravel, and the authority's value (or 0.70) for compacted gravel used by vehicles [To be confirmed].

7.2.5 Tc shall be calculated by a stated method appropriate to the runoff coefficient (for example, Airport Method for C below 0.40, Bransby-Williams for C of 0.40 and above), using measured flow lengths and slopes, and not less than the authority's minimum (commonly 10 to 15 minutes; INEAS default 10 minutes where none is set).

7.2.6 Pre-development conditions shall be delineated from existing survey, with a pre-development drainage plan. Any pre-development impervious area claimed shall be shown on a figure and verified from imagery, survey or historical approvals.

7.2.7 Time of concentration shall be computed by a method matched to the site, and the method shall be stated in the report:

  1. Simple site: one overland and one channel segment to the outlet. Use an empirical formula (for example the Airport Method where C is below 0.40, and Bransby-Williams where C is 0.40 or more, per 7.2.5).
  2. Complex site: segment-by-segment travel time (sheet flow, shallow concentrated flow, channel or pipe flow) from measured lengths and slopes, with the velocity or kinematic equation for each segment stated. Segment methods from US sources (for example NRCS TR-55) are acceptable only where the approval authority accepts them.
  3. Modelling: Tc is derived from a hydrograph model (7.2.2). The model inputs, routing parameters and storm (Chicago or AES, as the authority requires) shall be stated, and the result checked against method (a) or (b).

7.2.8 Where the authority's sewer design guideline applies, its inlet-time rules govern. The City of Ottawa Sewer Design Guidelines (October 2012, Section 5.4.5.1; superseded by SDG 004, December 2025, to be confirmed) use a 15-minute inlet time for backyard drainage structures and base downstream Tc on street sewer segments only.

7.2.9 Storm duration used for storage shall exceed twice the basin Tc, and the storm time step shall be short enough that peak flows are not overestimated (Ottawa Sewer Design Guidelines, 2012, Section 5.4; to be confirmed against SDG 004). Where the time step is less than 10 minutes, peak intensities may be averaged to a 10-minute step only with the authority's agreement.

7.3 Climate change

7.3.1 Where the authority requires a climate change adjustment, it shall be applied as specified. Where none is specified, a stress test shall be reported showing the effect of a [To be confirmed] increase in 100-year intensity on ponding limits and overland flow routes. No redesign is required for the stress test unless a building opening or the ROW is affected.

7.4 Quantity control

7.4.1 Post-development peak flows shall be controlled to the allowable release rate set by the authority, the CA or the governing master drainage plan. Where no rate is set, post-development peaks shall not exceed pre-development peaks for the 2-, 5-, 10-, 25-, 50- and 100-year storms (INEAS default).

Note: Some authorities set a stricter target, such as controlling all events to the 2-year or 5-year pre-development rate (for example, Cataraqui Conservation, Perth) or a unit release rate in L/s/ha. Always confirm at pre-consultation.

7.4.2 Each outlet shall be analysed separately. A summary table shall give pre and post peaks by catchment and by outlet, with a separate line for any flow to an MTO, county or regional ROW, and shall include uncontrolled areas.

7.4.3 Uncontrolled areas (roof edges, perimeter strips, entrances) shall be accounted for in the release calculation, and the destination of their 100-year flow shall be shown.

7.4.4 Where quantity control is waived, outlet erosion shall still be addressed.

7.5 Quality control

7.5.1 Quality control shall meet the authority's level. Where none is set, Enhanced protection (80% long-term TSS removal) under the MOE 2003 manual applies (INEAS default). Normal protection (70%) shall be used only where the authority accepts it.

7.5.2 TSS removal shall be demonstrated for the total tributary area, using a treatment train where one device is not enough, with explicit removal calculations.

7.5.3 Manufactured treatment devices shall be ISO 14034 ETV-verified, sized with the manufacturer's report attached, located correctly relative to the ICD, and credited only with the TSS removal the authority accepts (often 50%).

7.5.4 Phosphorus targets shall be met where a watershed plan or the authority sets one.

7.6 Erosion control and water balance

7.6.1 Where required, erosion control shall be provided by extended detention of the authority's design event (commonly 25 mm over 4 hours, released over 24 to 48 hours), with drawdown calculations.

7.6.2 Where required, a water balance shall show pre-development, unmitigated post-development and mitigated post-development conditions, with areas that sum and justified infiltration rates. The retention target (commonly the first 5 mm to 27 mm) shall be stated with its source. Retained volume shall have a defined pathway (infiltration, evapotranspiration or reuse).

7.6.3 Where no method is prescribed, the water balance may follow the MOE 2003 manual (Table 3.1), with annual precipitation taken from current climate normals or projections for the site and the source stated.

Note: The MECP draft LID guidance manual (2022) proposes a runoff volume control target based on the 90th percentile rainfall event. It is not final and shall be used only where the authority adopts it.

7.7 Low impact development

7.7.1 Every SWM report shall include an LID screening section. LID shall be considered first; where rejected, the reason shall be given.

7.7.2 Infiltration LID shall meet all of the following:

  1. in-situ infiltration testing at each LID location, with a design rate that applies a stated safety factor;
  2. at least 1.0 m separation from the bottom of the facility to seasonally high groundwater and to bedrock;
  3. drawdown within 48 hours, or the authority's limit (LSRCA area: see 7.7.6(e));
  4. setbacks from foundations, property lines, wells and septic systems;
  5. screening against source protection vulnerable areas (WHPA, SGRA, HVA) and contamination;
  6. pre-treatment for runoff from parking and vehicle areas; and
  7. details to the CVC/TRCA LID guide or CSA W200, including underdrain grades.

7.7.3 For small drainage areas, a drywell or other infiltration measure should be considered before piped or trench solutions.

7.7.4 Cisterns and reuse systems shall include drawdown calculations, a reuse demand balance and an O&M plan.

7.7.5 Draft LID volume target (informative, not yet adopted). The MECP draft Low Impact Development Stormwater Management Guidance Manual (January 2022, draft for consultation; ERO 019-4971) proposes a runoff volume control target equal to the 90th percentile rainfall event, and states that it is for informational purposes only. Where the approval authority has not adopted it, and outside the LSRCA area (see 7.7.6(b)), the design shall state the first 5 mm to 27 mm retention target used, with its source, and shall show the 90th percentile volume as a sensitivity case only.

7.7.6 Conservation authority LID guidance may apply in place of the draft manual. The LSRCA Technical Guidelines for Stormwater Management Submissions (January 2026) list a feature-based water balance report as a review item. Whether one is required depends on the applicable policy, and its scope is confirmed with the Authority. The January 2026 text names the Low Impact Development Stormwater Management Planning and Design Guide (2010) in Section 3.1 and the L.I.D. WIKI Guide in Section 6.4. It does not confirm that these are the same document. Within the Lake Simcoe Region Conservation Authority (LSRCA) area, the following apply, taken from Sections 3.2.4, 3.2.6 and 4.1 and Appendices B, L and M of the January 2026 Technical Guidelines:

(a) projects creating 0.5 ha or more of new impervious surface trigger volume control;

(b) new non-linear development shall retain the post-construction direct runoff volume from 25 mm of rainfall from all impervious surfaces, or the 12.5 mm flexible alternative in Section 3.2.6 where the site has restrictions;

(c) for commercial, industrial and institutional sites, infiltration may only be permitted from clean surfaces such as rooftops and landscaped areas;

(d) infiltration credit is not provided for amended topsoil thickness, for conveyance measures such as grassed swales, or for measures where the minimum flow path over a pervious surface is less than 5 m (Section 4.1, p. 26);

(e) infiltration credit is given only where every criterion in Appendix B, Section 1.2 is met, and no credit is given where any is not met. The criteria include a native infiltration rate of 15 mm/hr or greater, a safety factor of 2.5 and drawdown within 24 hours. Where this conflicts with the 48-hour limit in Clause 7.7.2, the more stringent limit shall govern;

(f) the maximum infiltration credit is 25 mm (Appendix B, Table 2);

(g) Appendix L: the direct runoff volume from 25 mm of rainfall from all impervious surfaces shall be captured and retained or treated on site, with no change to hydrologic parameters in the calculation; and

(h) Appendix M: a catchment-based water balance is generally required where a natural heritage feature is supported hydrologically. It uses the Thornthwaite-Mather method and at least one year of pre-development data, unless a governing study sets otherwise.

[To be confirmed]

7.8 Storage and control structures

7.8.1 Every control structure shall have the ICD type, size and location specified, labelled on the grading and servicing plans, with rating calculations using the orifice or weir equation, stated discharge coefficients and heads from the stage-storage table. Manufacturer data shall be attached for proprietary devices.

7.8.2 Minimum orifice size shall be the authority's minimum (for example, 100 mm in North Grenville). Where none is set, INEAS default is [To be confirmed].

7.8.3 Stage-storage and stage-discharge tables shall be provided for every storage element, and the rating curve shall match the stage-storage-discharge table. Swale storage shall account for longitudinal slope.

7.8.4 Control weirs and emergency spillways shall be separate, each with calculations and details.

7.8.5 Rooftop storage shall state volume, maximum depth (authority limit; for example 100 mm in Perth), drawdown time and number of drains, and shall be coordinated with the mechanical and structural engineers. Rooftop storage and orifice plates shall not be relied on where flows reach MTO drainage.

7.8.6 Underground storage shall be labelled by product and detailed, with an emergency overflow and frost protection, and shall not be placed under required parking where the authority prohibits it.

7.8.7 Ponds (wet, dry or combined with fire storage) shall follow the MOE 2003 manual geometry (Tables 3.2 and 4.6 as applicable): side slopes, permanent pool depth, forebay, 2- and 100-year levels, at least 0.3 m freeboard, inlets and outlets, maintenance access and safety barriers.

7.8.8 Storage credited in granular media (sand filter layers, clear stone, chambers) shall use the drainable (effective) porosity of the material from the geotechnical engineer or product data, not total porosity. Where no data exist, the value used shall be justified [To be confirmed].

7.9 Conveyance

7.9.1 The minor system shall be designed for the 5-year storm unless the authority specifies otherwise. The major system shall convey the 100-year (or Regional) storm.

7.9.2 Storm design sheets shall be provided for every segment with pipe material, class, length, slope, capacity and velocity. INEAS default: full-flow velocity 0.6 m/s to 3.0 m/s; design flow not over 80% of capacity where the authority requires it.

7.9.3 A 100-year HGL analysis from the outlet shall be provided where the site sewer connects to a municipal sewer, showing at least 0.3 m freeboard to the lowest USF or foundation drain connection, or the authority's greater value. Foundation drains shall be connected separately from roof drains above the HGL.

7.9.4 Inlet capacity shall be checked: no ponding in minor events in travelled areas; sag catch basins sized for the 100-year with 50% blockage.

7.9.5 Swales and ditches shall have conveyance and velocity calculations and lining for computed velocities.

7.10 Drainage area plans

Pre- and post-development drainage area plans shall show catchment IDs, areas, runoff coefficients and outlets that map one to one to the calculations and model, and grading arrows shall match the catchment boundaries.

7.11 Approvals and long-term obligations

7.11.1 The report shall state the ECA route for private SWM works: a direct MECP ECA, the municipality's CLI-ECA, or an exemption under O. Reg. 525/98, with the reason.

7.11.2 An operation and maintenance manual shall be provided for each SWM facility, OGS and LID feature.

7.11.3 Where municipal drains or field tiles are affected, they shall be documented and the drainage superintendent's sign-off obtained.

7.12 Reference to CSA W211:21

7.12.1 CSA W211:21, Management standard for stormwater systems (National Standard of Canada), provides guidance on the planning, design and construction of stormwater systems. This Standard refers to W211 as published, without restating it. The SWM report shall identify which W211 clauses apply to the project and how each is addressed.

7.12.2 [To be confirmed]

7.13 Provincial stormwater criteria (informative)

7.13.1 MTO Highway Drainage Design Standards (text dated November 2023). Where a discharge reaches a provincial highway or its drainage, the following apply, and the desirable value is used unless the authority sets otherwise. Supersession of the 2008 HDDS shall be confirmed with MTO before use.

  1. Surface drainage (SD-1): freeway, arterial and collector minor system 10% AEP (10-year), major 1% AEP (100-year); local road minor 20% AEP (5-year); depressed roadway minor 4% AEP (25-year), major 1% AEP (100-year).
  2. Storm sewers (SD-4): minimum pipe 300 mm; minimum lateral slope 0.015 m/m; maintenance hole spacing 150 m for pipes up to 1200 mm and 350 m above 1200 mm; trunk minimum velocity 0.75 m/s (smooth) or 0.9 m/s (corrugated), desirable, with 0.5 m/s minimum.
  3. Roadside ditches (SD-9): maximum minor-flow depth 1.0 m; minimum freeboard to subgrade 0.3 m; maximum side slope 2H:1V; minimum longitudinal slope 0.3%.
  4. Stormwater management level of control (SW-1): quantity control depends on receiving system capacity or an MTO-endorsed watershed plan, and the more stringent governs. Design flows at 2, 5, 10, 25, 50 and 100-year and the Regulatory flow. Quality control: enhanced about 80% long-term TSS removal (required where sensitive aquatic habitat will be affected); normal about 70%; basic about 60% (only where habitat is shown to be insensitive).
  5. Wet ponds (SW-2): drainage area 5 ha or more (desirable); 24 h desirable detention for the 40 m3/ha volume, extended to 60 h maximum; orifice 100 mm desirable, 75 mm minimum; 1.5 m desirable total active depth, 2.0 m minimum; side slopes 6:1 desirable within 3.0 m of the permanent pool, 5:1 minimum; forebay at least 1.0 m deep (1.5 m desirable); inlet and outlet pipes 450 mm minimum. Dry ponds draining less than 5 ha: detention up to 48 h. [To be confirmed]
  6. Culverts (WC-7, WC-8): freeboard at watercourse crossings 1.0 m for freeways, arterials and collectors, 0.3 m for local roads; minimum culvert 800 mm diameter on urban freeways and arterials, 600 mm on rural arterials and collectors, 500 mm on local roads over 10 m long and 400 mm on local roads of 10 m or less.

7.13.2 Ontario Stormwater Management Planning and Design Manual (March 2003), Chapter 3, used as the baseline for Section 53 OWRA reviews: long-term TSS removal of 80% (enhanced), 70% (normal) and 60% (basic); enhanced required where sensitive habitat is at risk. Peak flows shall not exceed pre-development values for storms from 2 to 100 years. Channels become unstable at about 10% watershed imperviousness, and the two-year storm is the usual erosion design event. Water balance by the Thornthwaite and Mather method is accepted where data are limited, with the Table 3.1 infiltration values as a check. Storage volume guidance for wet and dry ponds is given in Table 3.2 as m3 per hectare for 35%, 55%, 70% and 85% imperviousness (enhanced wet pond 140 to 250; normal wet pond 90 to 150; basic dry pond 90 to 240).

7.13.3 Units and totals in the 2003 manual's worked example (Table 3.1 net infiltration reduction) are not labelled in the source. Confirm units before quoting.

7.14 City of Ottawa criteria (where Ottawa is the approval authority)

Note: The values in Clause 7.14 are taken from the 2012 Sewer Design Guidelines and the 2016 staff revision summary. The current edition is SDG 004, Fourth Edition (December 2025). Every value in this clause shall be confirmed against SDG 004 and bulletin ISTB-2018-01 before design use.

7.14.1 The City of Ottawa minimum submission content for on-site SWM (Section 2.0) requires a grading and drainage plan stamped by a P.Eng., a servicing plan, a SWM brief or QuickSWM summary, and a geotechnical report where infiltration is proposed. The City's Quick SWM tool (version 1, 2025) is the first-pass screen.

7.14.2 Minor system (2016 staff revisions to the stormwater design guidelines, implemented through technical bulletin ISTB-2018-01): minimum storm sewer design for local streets at the 2-year event without ponding; collector streets at the 5-year event; arterial roads at the 10-year event. Maximum HGL remains 0.3 m below the underside of footing.

7.14.3 Major system: maximum static plus dynamic depth on local and collector streets 0.35 m at the 100-year event; a 15 cm vertical clearance between the spill elevation and the ground at the building envelope; the water level shall not reach any part of the building envelope, including the underside of footing.

7.14.4 Stress test: the 100-year intensity increased by 20% is used to check that the water level remains below the lowest building opening, and that the storm sewer HGL remains below the underside of footing.

7.14.5 Rear yard swales or ditches modelled as attenuation: minimum slope 1.5%, minimum depth 150 mm, maximum depth 600 mm, maximum side slope 3H:1V.

7.14.6 Sanitary design (Ottawa Sewer Design Guidelines, 2012, Section 4; to be confirmed against SDG 004): residential peak factor by the Harmon equation (K = 1 for the design of the sanitary system); commercial and institutional peak factor 1.5; industrial peak factor from Appendix 4-B; infiltration allowance 0.28 L/s per effective gross hectare; foundation drain allowance 5.0 L/s per gross hectare where required.

7.14.7 Storm design (Section 5): Rational Method and Manning's equation are acceptable where the drainage area is under 40 ha and the outlet is not submerged. The 100-year design storm is the 3-hour or 6-hour Chicago storm (Table 5.2) or the AES distributions (Figures 5.1 and 5.2). The IDF data in the 2012 guideline (Table 5.1, 1967 to 1997) are historic and shall be checked against current City IDF data before use.

7.14.9 Water distribution and fire flow criteria in the City of Ottawa Design Guidelines (Water Distribution, July 2010) were not reviewed in this edition. [To be confirmed]

7.14.10 Limit note: the 2016 revision summary is a staff presentation. Its values shall be confirmed against bulletin ISTB-2018-01 before design use. That bulletin was not available in machine-readable form when this edition was prepared.

7.14.11 Note (under development): the full text of SDG 004 (December 2025) was not available when this edition was prepared. Clause 7.14 values remain subject to confirmation against SDG 004 before design use.