Site Servicing, Erosion and Sediment Control, and Construction Verification
INEAS SD-100:26, clauses 8 to 10. Preliminary draft.
8 Site servicing
8.1 General
8.1.1 Site servicing shall be designed to the authority's standards and, where they are silent, to the MOE (2008) Design Guidelines for Drinking-Water Systems and Design Guidelines for Sewage Works.
8.1.2 Before detailed design, as-built records and plan-and-profile drawings of the receiving services shall be obtained, and existing services shall be daylighted where inverts, forcemains or clearances are uncertain.
8.1.3 Municipal standard notes and details shall be used unaltered where they exist; OPSD shall be used only where no municipal detail exists. Inapplicable references shall be removed.
8.1.4 Every existing service shall be shown as reused or decommissioned (water blanked at the main, laterals capped), unless the authority directs otherwise.
8.2 Water
8.2.1 Water demands (ADD, MDD, PHD) shall use the authority's current rates by use and the correct peaking chain, reconciled with the architectural program and the mechanical engineer's fixture-unit demand.
8.2.1.1 Where use-specific demand data are not available, area-based allowances from the MOE (2008) drinking-water guidelines may be used, with the section cited. Peaking factors shall be the authority's or those of the MOE (2008) guidelines for the equivalent population, and shall be stated with their source.
8.2.2 Fire flow shall be calculated by FUS (2020) or the method the authority or OBC Div. B 3.2.5 requires, and shown against boundary conditions or a recent hydrant flow test with static and residual pressures. Boundary conditions shall be dated and requested again at each submission.
8.2.3 Pressures shall be checked against the authority's range; PRVs shall be shown where pressures exceed the maximum.
8.2.4 Water services shall show size and material, domestic and fire split at the property line, isolation valve and box at each municipal connection, curb stop at the public/private limit, meter location (coordinated with the architect), backflow prevention, and bends and stubs per unit. Services shall not run under other units.
8.2.5 Hydrants shall be within the distances set by OBC Div. B 3.2.5 and the fire department (commonly 90 m to the principal entrance and 45 m to the FDC). The FDC frontage shall be kept clear.
8.2.6 Dead-end watermains shall be looped or justified. Where a private watermain is looped, it should be laid out for possible municipal assumption: a 5 m easement, under asphalt, clear of buildings, rigid surfaces and trees.
8.3 Sanitary
8.3.1 Sanitary flows shall use the authority's rates and peaking factors, in the authority's design sheet format, with downstream capacity checked where required (including combined sewer overflow risk in combined areas).
8.3.2 A single sanitary connection with an inspection manhole shall be provided for condominium and multi-building sites. The inspection manhole shall be on private property within the authority's distance of the property line (commonly 1.5 m).
8.3.3 Laterals shall not exceed the main in size; a manhole shall be provided where the lateral exceeds 50% of the main diameter; connections shall be perpendicular, with the invert at or above the springline of the main.
8.3.3.1 Sanitary laterals shall achieve the authority's minimum velocity (commonly 0.6 m/s) at design flow. Where the authority's minimum pipe size cannot achieve it at the expected flow, the design shall show the effect (for example, by peak daily flow) and obtain the authority's acceptance of the size or slope.
8.3.4 Foundation drains shall not connect to the sanitary sewer.
8.4 Storm
Storm services shall meet Clause 7.9. Each building shall have the separate service connections the authority requires.
8.5 Pipe data, cover and separation
8.5.1 The servicing plan shall show for every pipe: size, material, class, slope, length, inverts and cover; and for every structure: ID, type, rim and inverts. Every lateral shall show length and slope.
8.5.2 Cover shall meet the authority's frost cover (for example, 2.0 m in Cornwall; 2.4 m for watermains in Ottawa). Where cover is less, insulation shall be designed and detailed.
8.5.3 A crossing table shall list every watermain and sewer crossing with vertical separation. Separations shall meet MECP Procedure F-6-1 and the authority's standard (2.5 m horizontal and 0.5 m vertical, or approved protection), and shall be labelled at every crossing and close parallel run.
8.5.4 Easement width plus the trench zone of influence shall be checked against foundations.
8.6 Private services
8.6.1 On rural sites, the septic system and well shall be located, with records obtained from the municipality or health unit at project start, and setbacks shown on the civil drawings.
8.6.1.1 Wells shall be constructed and protected under R.R.O. 1990, Reg. 903. Where a well is near vehicle traffic, the wellhead shall be protected by a steel casing and bollards. Separations between wells, septic tanks, leaching beds, buildings and property lines shall meet OBC Div. B Part 8 [To be confirmed].
8.6.2 Daily design sewage flow shall be tabulated (existing plus proposed). Jurisdiction shall be confirmed at concept: OBC Part 8 for systems up to 10,000 L/day; MECP ECA above that.
8.6.3 Where total sewage flows exceed 4,500 L/day, or the authority requires it, a servicing options report and hydrogeological assessment under MECP Procedures D-5-4 and D-5-5 shall be provided.
8.6.4 Any addition on a septic lot shall be checked for Part 8 capacity.
8.6.5 Space for future septic expansion should be reserved on industrial and commercial lots.
8.7 Service sizing
8.7.1 Water services shall be sized for the design demand (and fire service where combined) by velocity and head loss, comparing standard sizes. Velocity shall not exceed 3.0 m/s (MOE 2008) or the authority's lower limit, and residual pressure at the building shall meet the mechanical engineer's requirement. The authority's minimum size and material govern (for example, 20 mm Type K copper in Brockville).
8.7.2 Sanitary and storm laterals shall be sized for design flow at not more than the authority's maximum depth of flow, with full-flow velocity between 0.6 m/s and 3.0 m/s unless the authority sets other limits, and minimum grade per the authority (commonly 1%, 2% preferred).
8.8 Utilities
8.8.1 Hydro, gas, telecommunications and lighting shall be coordinated in a composite layout, with clearances to the utility owners' standards and to the services in Clause 8.5.
8.8.2 Hydro service voltage and demarcation should be confirmed at concept.
8.8.3 Gas installation shall be sequenced before final surfaces; abandonment of existing gas services shall be requested well in advance.
8.9 Construction near existing infrastructure
Where work is near critical municipal infrastructure, the drawings shall note hydro-vac excavation, protection measures and a pre-construction meeting. Pre- and post-construction CCTV of receiving sewers and condition surveys should be budgeted.
9 Erosion and sediment control
9.1 A stand-alone ESC plan, sealed by a P.Eng., shall accompany every SWM report or brief that supports a site plan, and every grading plan where soil is disturbed.
9.2 The ESC plan shall be phased where grading is phased, and shall show as applicable: construction access and mud mat; silt fence (heavy-duty at sensitive limits); catch basin and inlet protection; interim swales, outlets and sediment traps or ponds (sized); stockpile locations and protection; dewatering discharge treatment; tree protection fencing; and the limit of disturbance.
9.3 ESC notes shall cite OPSS.MUNI 805 and the authority's or CA's ESC guideline, name every road authority whose ROW may be affected, and include inspection, repair and removal requirements, including inspection after each rainfall event above the authority's threshold.
9.4 Where the municipality holds a CLI-ECA, ESC notes shall reference its conditions.
9.5 ESC and tree protection shall be installed and inspected before any site disturbance. Pre-grading approvals and CA permits shall be in hand first.
9.6 Inspection and monitoring of ESC measures shall follow CAN/CSA-W202.
9.7 Environmental notes shall include the vegetation clearing window for migratory birds, watercourse setbacks and any EIS commitments, including wildlife exclusion fencing shown separately from silt fence.
9.8 Groundwater discharge during construction shall be tested and permitted under the sewer use by-law, EASR or PTTW as applicable.
9.9 Stockpiles of topsoil and excess soil shall be located outside the flow route and the critical root zone of retained trees, protected with perimeter sediment control, and stabilized within the period the authority or the Standard requires. Stockpile height and side slope limits shall be stated on the ESC plan [To be confirmed].
9.10 Erosion control design shall be checked against the shear stress of the design flow at every outlet and channel, using the critical shear strength of the soil. Where the computed shear exceeds the critical value, the outlet shall be armoured or a stilling measure provided. Erosion thresholds are set by the authority; the Ontario Stormwater Management Planning and Design Manual (2003) uses the two-year storm as the usual erosion design event.
10 Construction verification
10.1 Tolerances
10.1.1 As-constructed grades shall be within 100 mm of design elevations, or within the authority's tighter tolerance (for example, 50 mm in Brockville).
10.1.2 As-constructed finished grade shall be at least 150 mm below TF, and window wells shall project at least 100 mm above finished grade.
10.1.3 Surface slopes, swale grades and depths, and slopes away from buildings shall meet Table 6.1 after final surface treatment.
10.2 Hold points
The design shall identify the stages at which engineering review is needed before work is covered. As a minimum:
- subgrade and engineered fill before placement of structures or pavement;
- pipe bedding and services before backfill;
- ICD, OGS, underground storage and LID installation before backfill or planting;
- ponds and swales at final grade before seeding or sodding; and
- final grades before acceptance.
10.3 Testing
10.3.1 Watermains and water services shall be pressure tested and disinfected to the authority's standard and AWWA C651.
10.3.2 Sewers shall be tested and inspected (leakage, deflection, CCTV) to the authority's standard.
10.3.3 Compaction shall be verified against the geotechnical engineer's requirements.
10.4 Basis of certification
Certification of grading, servicing and SWM works shall be based on a survey of as-constructed elevations and inverts by an OLS, together with field review at the hold points in Clause 10.2. Items not reviewed shall be excluded from the certification.