General Requirements, Site Information and Grading and Drainage
INEAS SD-100:26, clauses 4 to 6. Preliminary draft.
4 General requirements
4.1 Professional responsibility
4.1.1 Every engineering drawing, calculation and report shall be prepared or checked under the direct supervision of a licensed Ontario P.Eng. and shall be sealed, signed and dated before issue to an approval authority. This includes grading, servicing, SWM, ESC, retaining wall and cost estimate documents.
4.1.2 The SWM report shall be prepared by a P.Eng. with water resources experience. When the site plan changes after a report is issued, the report shall be updated or the author shall issue a letter confirming it still applies.
4.1.3 Work outside INEAS's licensed scope (landscape architecture, surveying, hydrogeology, acoustics, ESA) shall be prepared by the appropriate qualified person and coordinated as recorded in the design basis under Clause 4.3.1.
4.2 Datum, units and base information
4.2.1 All drawings and reports shall be in SI units.
4.2.2 All elevations shall be geodetic and tied to a published benchmark. The benchmark location, description and elevation shall be shown on the grading plan. An assumed datum shall be used only where the approval authority permits it in writing.
4.2.3 Horizontal datum shall be stated. Drawings shall be georeferenced to NAD83 UTM (Zone 17 or 18 as applicable) where the approval authority requires CAD submissions.
4.2.4 The base plan shall be a current boundary and topographic survey by an OLS, with the source and date stated. All plans in a submission shall use the same base.
4.2.5 Existing grades shall extend beyond the property line by the distance the approval authority requires. INEAS default: 6 m, and not less than 3 m.
4.3 Criteria confirmation
4.3.1 The design basis shall state the design criteria that apply: design storms, IDF source, release rates, quality target, water balance target, minimum slopes, cover, and any secondary plan, master drainage plan or watershed criteria.
4.3.2 Each criterion shall be cited to its source document and edition, or to the pre-consultation record. Criteria from another municipality shall not be used as the basis of design unless the approval authority accepts them in writing.
4.3.3 Where interim and ultimate conditions differ (for example, a road reconstruction that is designed but not scheduled), both shall be designed and shown, and the approval authority shall confirm the interim condition in writing.
4.4 Deviations
4.4.1 Any deviation from the approval authority's standards shall be identified, justified and accepted in writing before the submission that relies on it.
4.4.2 Any deviation from this Standard shall be approved by the project's principal engineer and recorded in the decision log.
5 Site information and design constraints
5.1 Site information
5.1.1 The design shall be based on the following information, current for the site:
- a boundary and topographic survey by an OLS (Clause 4.2.4);
- a geotechnical investigation sealed by a P.Eng. or P.Geo. covering soils, seasonally high groundwater, bedrock or refusal depth, pavement structure, pipe bedding, grade-raise limits, slope stability where applicable, and infiltration rates where infiltration is proposed;
- a hydrogeological assessment where private wells or septic systems, dewatering or infiltration in a sensitive area are proposed (Clause 8.6);
- records of existing services and utilities, each with its source and quality level (as-built, record drawing, survey, or subsurface investigation at quality levels A to D under CSA S250), confirmed by daylighting where an invert or clearance governs the design;
- water boundary conditions or a hydrant flow test not older than the authority's limit [To be confirmed]; and
- hydrologic soil group, from site testing or published soil mapping (for example, AgMaps), stated with its source.
5.1.2 Geotechnical, hydrogeological and environmental data older than the authority's limit shall be updated, or covered by a reliance letter from the author.
5.2 Design constraints
The design shall identify, plot and respect:
- flood, erosion and dynamic beach hazards, wetlands and the CA regulation limit (O. Reg. 41/24), with geodetic regulatory flood levels;
- natural heritage features and their setbacks (commonly 30 m from wetlands and watercourses);
- MTO permit control limits under the Public Transportation and Highway Improvement Act, including setbacks for buildings and integral features;
- road widenings, 0.3 m reserves and sight triangles required by the road authority;
- source protection vulnerable areas (WHPA, IPZ, HVA, SGRA) and the policies that apply to the proposed activities;
- municipal drains and field tiles under the Drainage Act;
- easements and rights-of-way on title, with their widths; and
- existing infrastructure in or near the site that the works could affect (trunk mains, forcemains, high-pressure gas, hydro), with its clearance requirements.
6 Grading and drainage
6.1 Objectives
Grading shall drain every building and paved area positively to a legal outlet, keep runoff from concentrating onto neighbouring land, provide a safe route for flows above the design storm, and meet the barrier-free and fire access slope limits.
6.2 Drainage to neighbours
6.2.1 Grading and drainage shall be contained on the site, or written permission-to-grade shall be obtained from the neighbouring owner or road authority.
6.2.2 Post-development runoff shall not be concentrated onto adjacent lands. Where neighbours have a known drainage complaint, the 5-, 25- and 100-year flows to each boundary shall be quantified and shown to be reduced or unchanged.
6.2.3 External drainage entering the site shall be identified from survey and CA contour mapping, captured and conveyed. External catchments shall not be diverted without justification and the approval authority's acceptance.
6.2.4 No grading shall occur in a county, regional or provincial ROW without that authority's permit. Grades shall tie in at the property line.
6.3 Building elevations
6.3.1 FFE, TF and USF shall be shown for every building and unit, and for adjacent buildings where grading ties in.
6.3.2 Finished grade at the building shall be at least 0.15 m below TF (INEAS default, matching common municipal practice), and shall slope away from the building.
6.3.3 USF and basement slabs shall be set above seasonally high groundwater using the full monitoring record. INEAS default: USF at least 0.3 m above seasonally high groundwater unless the geotechnical engineer designs for permanent dewatering or waterproofing.
6.3.4 Where a site is in or near a CA-regulated flood hazard, the regulatory flood level shall be plotted on the grading plan, and floodproofing elevations shall be shown geodetically on the architectural sections.
6.4 Slope criteria
6.4.1 Slopes shall meet the approval authority's criteria. Where none are published, the INEAS defaults in Table 6.1 apply.
Table 6.1 — Grading slope criteria
Element | Range found in municipal standards | INEAS default | Basis |
|---|---|---|---|
Grassed / landscaped surfaces, minimum | 2% | 2.0% | Comprehensive Checklist; Final Grading Checklist |
Within 4 m of a building | — | 2–4% away from the building | IFP Drawings Checklist |
Grassed surfaces, maximum (lawn areas) | 5–7% before a terrace or slope treatment | 7% | Municipal (Ottawa) |
Side slopes and landscape areas, maximum | 3:1 (4:1 preferred in some municipalities) | 3:1; 4:1 where mown | Comprehensive Checklist |
Paved surfaces, minimum | 0.5–2.0% | 1.5% | Comprehensive Checklist |
Swale longitudinal slope, minimum | 1.0–2.0% | 2.0% | Comprehensive Checklist; Final Grading Checklist |
Swale depth, minimum | 150–200 mm | 150 mm; 200 mm on rear lot lines (Brockville) | Municipal |
Swale side slopes, maximum | 3:1 | 3:1 | Comprehensive Checklist |
Driveway grade | Commonly max 5% over the first 7.5 m from the ROW | 2% min, 10% max; authority limit near the ROW governs | Final Grading Checklist |
Unheated vehicle ramp, maximum | — | 10% | Comprehensive Checklist |
Walkway running slope, maximum | O. Reg. 191/11 | 5% (8% where designed as a ramp) | Comprehensive Checklist |
Sidewalk crossfall | — | 2% min, 4% max | Comprehensive Checklist |
Boulevard / ROW grades | Maximum 2% in some municipalities | Per road authority | Municipal |
Lot grading, overall | 2–6% | 2–6% | Municipal |
Finished grade below TF | 150 mm | 150 mm | Final Grading Checklist |
Window wells above finished grade | — | 100 mm | Final Grading Checklist |
As-constructed grade tolerance | 50 mm (Brockville) to 100 mm | 100 mm, or the authority's tighter value | Final Grading Checklist |
Note: Ranges are taken from the municipal standards listed in Annex A. INEAS defaults apply only where the approval authority has no criterion of its own.
6.5 Ponding and overland flow
6.5.1 The emergency overland flow route shall be shown on the grading plan, not only in the report, with flow arrows, spill elevations and the route to the street or other safe outlet, including across neighbouring lands where it crosses them.
6.5.2 Overland flow routes shall be checked against building openings, window wells and vents. INEAS default freeboard from the 100-year ponding or spill elevation to the lowest opening: 0.30 m [To be confirmed].
6.5.3 Ponding limits and maximum elevations shall be shown for each design event. No ponding shall occur in the ROW, fire routes, barrier-free routes or accessible stalls. Maximum ponding depth in parking areas: per authority, commonly 0.25–0.30 m.
6.5.4 Entrances shall be detailed for drainage: entrance grades, culvert size and inverts after fill, and spill to the roadside ditch. Culvert sizing or the entrance permit shall accompany the submission.
6.6 Grading near buildings, swales and infiltration areas
6.6.1 Ground within 4 m of a building shall slope away from it at 2% to 4%.
6.6.2 Landscaped areas designed to hold water for infiltration may be graded flatter than Table 6.1, to not less than 0.5%, only where they are more than 4 m from a building, outside the overland flow route, and accepted by the authority.
6.6.3 Vegetated swales steeper than [To be confirmed] shall have velocity calculations and erosion protection designed for the computed velocity.
6.7 Retaining walls
6.7.1 Proposed grades shall be checked against existing retaining walls.
6.7.2 Walls of 1.0 m or more in exposed height shall be designed, detailed and sealed by a P.Eng., with global stability checked and guards provided where required. Walls shall be numbered consistently with the wall designer's drawings.
6.7.3 Wall footings shall be dimensioned to the property line and shall not encroach on the ROW or neighbouring land.
6.8 Fill and excess soil
6.8.1 Imported fill and excess soil shall be managed under O. Reg. 406/19. Unsuitable material shall be disposed of under OPSS.MUNI 180.
6.8.2 In a regulated area, a fill plan with cut and fill quantities shall be provided where the CA requires it.
6.8.3 Excess soil shall be managed under O. Reg. 406/19 (On-Site and Excess Soil Management, made under the Environmental Protection Act), as amended by O. Reg. 235/25 (made 23 October 2025). The current consolidation shall be checked before each issue of the Standard or a project submission.
6.8.4 Where the regulation requires an excess soil management plan, it shall be prepared with its contents, qualified person and registry filing as the regulation requires, and the owner, project leader and soil management contractor responsibilities shall be stated on the grading plan notes.
6.8.5 Excess soil quality shall be compared with the Excess Soil Quality Standards in Part II of the Rules for Soil Management and Excess Soil Quality Standards, as referenced in the regulation at the time of issue.
6.8.6 Tracking and registration thresholds and exemptions shall be taken from the current consolidation of O. Reg. 406/19 as amended. [To be confirmed]